Design Team leader
Project Managers / Architects
Cost Management
Building Services Engineering
Civil & Structural Engineering
Service
Value
€13.5 million
Design
25 weeks
Procurement
07 weeks
Build
60 weeks
Stage
Complete
Footprint
3000 m2 (32,290 ft2)
Project Deliverables
Detailed Survey and Generation of BIM 360 Model
Scheme and Detail Design Reports and Presentation
Corporate Presentations and Reports
Hazard & FMEA Analysis
Value Engineering Workshops
Budget Cost Analysis at each Design Phase
PSDP and Preliminary SHW Plan
Statutory Compliance & Fire Engineering
Procurement / Contract Strategy
Tender Process and Reporting
IFC Documentation
Site Support & Contract Administration
Resident Engineering Services
Snagging / Handover
Final Account Negotiation
Safety File and O&M Review
This project was the first major expansion undertaken by our clients since the initial greenfield build in 2005. Some of the principal clients personnel involved in the original startup project were engaged in the delivery of this Mix and Fill Suite project and as a result, knowledge sharing and site experience was crucial to the successful delivery of the project.
Overview
Expansion projects have many challenges for the client: relocation of production activities, decommissioning of redundant equipment and services, contractors’ intervention into a live operation facility, identification of contractor access points, removal of waste material, potential impact on existing emergency/personnel routes, contractor materials delivery and placement.
To mitigate these risks TG implement our Risk and Opportunity strategies so risks to production or general client activities were identified, assessed and prudent mitigation methodologies were put in place to protect our clients’ activities for the duration of the site operations stage.
Taylor Group was engaged to undertake the design of an expansion project to ensure the facility retains capacity to meet anticipated global demand for Diagnostic Products. The project was developed as an extension to the existing facility comprising an employee entrance, mix tank complex, filling suite, packaging hall, coldstore, warehouse, technical floor, conference room, laboratories, energy hub upgrades, associated supporting accommodation and general site works and services.
Critical to the success of the project was the upgrading of existing utilities to service the new facility.